Add as a preferred sourceThe Rockaway Township Zoning Board of Adjustment is scheduled to adopt a resolution Tuesday, Nov. 17, on JCP&L’s application to upgrade its Fleetwood Substation at 50 Mount Hope Road, a plan that includes an 8-foot security fence around the site, according to the board’s Nov. 17 agenda.
The public hearing on the application was held at the board’s Oct. 20 meeting, according to the utility’s public hearing notice and the Oct. 20 agenda, which listed it as BOA #26-09 under Public Hearing. On Nov. 17 it appears under Resolutions instead, alongside approval of the Oct. 20 minutes. A zoning board resolution puts a decision the board has already made into writing. The agenda does not say whether the board approved or denied the application, and the Oct. 20 minutes had not been posted on the Township’s website as of Tuesday morning.
The Nov. 17 meeting begins at 7 p.m. at the Municipal Building, 65 Mount Hope Road. The only public hearing on that night’s agenda is a separate porch variance application for 27 Johnson Road.
What JCP&L asked for
According to the notice, JCP&L plans to replace the substation’s existing switchgear, breaker and bus equipment on new concrete slabs, with the upgraded equipment housed in a metal-clad enclosure. The project adds a perimeter security fence with manual swing gates, and a temporary mobile unit would keep the substation running during construction.
The substation sits in the R-20 single-family residential zone, where public utility uses are not expressly permitted, so the application sought a use variance to expand the existing utility use. It also sought bulk variances for the 8-foot fence in the front, side and rear yards, where the Township allows fences of 4 to 6 feet, and for a rear yard setback of 13.4 feet where 50 feet is required. The notice says the 13.4-foot setback already exists today.
What residents can do
Because the hearing has closed, the Nov. 17 resolution is not a public hearing on the plan. Residents can still speak during the agenda’s general Open to the Public portion (item 6). To see the plans or ask for a copy of the resolution once it is adopted, contact Board Secretary Jamie Browne at 973-983-2809 or jbrowne@rockawaytownship.org. The application is on file at the Municipal Building during regular business hours.
Rockaway Township and Rockaway Borough are separate municipalities in Morris County. The Fleetwood Substation is in Rockaway Township.
Correction: An earlier version of this story said the zoning board would take up the plan Nov. 17. The public hearing was held Oct. 20; the board is scheduled to adopt a resolution on the application Nov. 17.